Last week, our construction team:
- finished pouring the last of the larger retaining and brace frame walls;
- began installing waterproofing along certain retaining walls, as well as footing drains;
- completed vapor barrier and wire mesh install.
This week:
- Slab pour!
- Waterproofing the poured walls, which lets us prepare for backfill.