1Page 1 of 1

Now viewing articles posted in 2025.

  • August 29 Update

    September 2nd, 2025


    August 29 Update
    This week, our construction team:completed the backfill for the last catch basin on N 150th and Burke Ave,poured more concrete footings,ran the deep underground storm piping under the building footprint,completed the form work for several concrete walls.  Next week: Rebar install for walls begins...

    Read More

  • August 22 Update

    August 25th, 2025


    August 22 Update
    From W. G. Clark Construction:This week, the team:Poured the first concrete of the project! Basement and elevator pit footings are poured, and we laid out the level-two footings. Finished up the last of the catch basins on N 150th St and laying pipe for the sewer connection on the west side of the ...

    Read More

  • August 15 Update

    August 18th, 2025


    August 15 Update
    From W. G. Clark Construction:This week, our team:Continued on more catch basin and storm pipe install in the right of way.Completed the digging and layout for the basement footings. Next week we start concrete!Finished running the sewer piping into the building footprint.Looking ahead to next week:...

    Read More

1Page 1 of 1